Calculator · Free
Concrete Calculator
Calculate cubic yards for slabs, footings, columns and stairs, with waste allowance.
Order this much concrete
3.50cubic yards
- Finished volume2.963 cubic yards before waste
- 80.0 ft³
- Estimated material cost3.50 yd³ at $165 per yard
- $578
- Ready-mix trucksA full load is 10 yd³
- 1 truck
- 60 lb bags0.45 ft³ each
- 196 bags
- 80 lb bags0.60 ft³ each
- 147 bags
Round up, and order the extra
This is past the point where bags make sense
| Step | Figure | Detail |
|---|---|---|
| Slab area | 240.0 sq ft | 20.00 ft × 12.00 ft |
| Thickness in feet | 0.333 ft | 4.00 in ÷ 12 |
| Finished volume | 80.00 ft³ | Sum of the geometry above |
| Converted to yards | 2.963 yd³ | 27 cubic feet per cubic yard |
| Waste allowance at 10% | 0.296 yd³ | Subgrade variation, spillage, form deflection |
| Rounded to the quarter yard | 3.50 yd³ | Ready-mix is sold in quarter-yard increments |
| Order | 3.50 yd³ | $578 |
| Option | Quantity | Total weight | Notes |
|---|---|---|---|
| Ready-mix delivery | 3.50 yd³ | 7.1 tons | Short load — expect a fee of roughly $60–150 per yard below a full truck |
| 80 lb bags | 147 bags | 5.9 tons | 3.5 pallets at 42 bags each |
| 60 lb bags | 196 bags | 5.9 tons | 3.5 pallets at 56 bags each |
Volume only. Reinforcement, vapor barrier, base gravel, forms and finishing are separate line items, and on a slab the compacted base course usually costs more to get right than the concrete does. Concrete weight is figured at 4,050 lb per cubic yard, which is typical for a normal-weight mix.
What this assumes
- One cubic yard equals 27 cubic feet.
- Default waste allowance is 10%, appropriate for typical subgrade variation.
- Bag yields assume 0.45 cubic feet per 60 lb bag and 0.60 cubic feet per 80 lb bag.
Important
Ready-mix is sold in fractional yards with a short-load fee below a full truck. Ordering short and needing a second truck creates a cold joint — always round up.
Understanding the result
Always round up
Running out of concrete mid-pour creates a cold joint, a permanent plane of weakness in the slab. Concrete is cheap relative to a failed pour, so order the next quarter yard up. Excess can go into a sidewalk pad or a footing.
Bags versus ready-mix
Bag mix is practical up to roughly half a cubic yard — about 40 sixty-pound bags. Beyond that the labor and the risk of inconsistent mixing make ready-mix both cheaper and better. A short-load fee is worth paying.
You may also need
The next decision usually follows directly from this one.
- CalculatorFraming Material CalculatorCount studs, plates, headers and sheathing for a wall from length, height and spacing.
- EstimatorRenovation Cost EstimatorEstimate a kitchen, bath, basement or addition project by scope, finish level and region.
- CalculatorDeck Material CalculatorEstimate joists, beams, decking, fasteners and footings for a deck frame.