Change order template

A change order records work outside the signed scope — with a description of the change, price or T&M rates, schedule impact, and signatures before extra work proceeds — so margin and collections survive the “while you’re here” request.

Generator

Fill in and export PDF

Complete the fields below and export through your browser print dialog to PDF. Nothing is uploaded to our servers — save the file where you keep customer records.

Company & customer

Describe what is included and key exclusions.

Line items

Total: $0.00

Change orders may be enforceable only when your master contract requires written approval. This generator is not legal advice.

What this template is for

Change orders are how fixed-price jobs stay profitable after demo opens walls or the customer changes selections. This generator produces a one-page PDF you can attach to email or print on site.

Every change order should reference the original contract or estimate number, describe added or deleted work in measurable terms, and state whether price is lump sum or time-and-materials with a not-to-exceed cap.

Not legal advice — match your master contract’s change-order clause and have an attorney review your template for projects above your risk threshold.

When to stop work

If the customer will not sign before you proceed, decide deliberately: some shops absorb small favors; others never move without ink. Inconsistent policy creates entitlement.

Photo the condition that triggered the change and attach to the PDF file — collections and disputes are won on documentation, not memory.

Required clauses

Missing reference to the base contract or approval signatures are the two fastest ways to eat change-order revenue.

  • Reference contract / estimate number and date
  • Description of change (added, deleted, substituted)
  • Price (lump sum or T&M with cap)
  • Schedule impact (days added or none)
  • Payment due (with progress bill if applicable)
  • Authorization signatures before work proceeds

Copy-ready clause library

Paste and adapt — align with your master agreement.

Scope delta

“Contractor will install [description] in addition to the scope in Agreement #[number]. Work listed in the original scope marked ‘deleted’ will not be performed.”

Added and deleted work in one document prevents scope creep in both directions.

T&M cap

“Change priced time-and-materials at shop rates in Exhibit A, not to exceed $[amount] without further written approval.”

Caps protect the customer and give you a stop point for discovery work.

Schedule

“This change adds [number] working days to substantial completion, weather and material lead times excepted.”

Sets expectation when the customer wanted the job done ‘next Friday.’

Common mistakes

Verbal approvals and lump sums with no photos are where remodel margin goes to die.

  • Proceeding without signature on structural or code-driven extras
  • Change order with no tie to original contract number
  • Lump sum with no schedule impact noted
  • Letting many small unsigned changes stack into one big dispute

Related

FAQ

Does a change order need a new contract?
Usually it is an amendment incorporated by reference — your master agreement should say so.
Can customers refuse to pay unsigned changes?
Often yes — that is why you stop or absorb deliberately, not accidentally.
Lump sum or T&M for unknown work?
T&M with a cap for discovery; lump sum when takeoff is clear.
Should change orders include photos?
Yes — attach conditions that justified the change.
Who signs?
Owner or authorized agent — get the name on the contract.
Do I need a change order for credit?
Document deleted scope and price reduction in writing too — avoids ‘you owe me’ later.