Bathroom Remodel Planner
Budget range, trades sequence, duration, hidden costs and contractor questions for a bath remodel.
Budget range
$18,243
to $22,703 · 3–7 weeks
| Category | Low | High |
|---|---|---|
| Demolition & haul-off | $1,213 | $1,510 |
| Plumbing rough & finish | $2,340 | $2,912 |
| Shower / tub package | $3,420 | $4,256 |
| Glass enclosure | $1,260 | $1,568 |
| Tile & waterproofing (shower + floor) | $3,456 | $4,301 |
| Vanity & top | $1,440 | $1,792 |
| Toilet install | $585 | $728 |
| Faucet & trim | $378 | $470 |
| Shower niche / shelf | $405 | $504 |
| Flooring (non-wet areas) | $600 | $746 |
| Electrical (GFCI, circuits) | $990 | $1,232 |
| Vanity & shower lighting | $612 | $762 |
| Exhaust fan / ventilation | $675 | $840 |
| Paint & trim | $554 | $690 |
| Permits & inspections | $315 | $392 |
- Trade sequence
- Demo & rough plumbing → Rough electrical & exhaust → Waterproofing & tile → Fixtures & glass → Paint & punch list
- Trades involved
- Bath remodeler or GC, Licensed plumber, Electrician, Tile setter
| Item | Quantity |
|---|---|
| Cement board / waterproof membrane | 132 sq ft |
| Floor tile | 45 sq ft |
| Thinset & grout | 4 bags |
| Vanity | 1 (spec in contract) |
| Toilet | 1 (model # in contract) |
| Shower valve & trim kit | 1 set — brand in quote |
| Exhaust fan | 1 — CFM sized to room volume |
| Faucet & drain assembly | 1 set — finish matches hardware |
| Vanity / shower lights | Qty per plan — wet-rated in shower zone |
| Shower niche box | 1 — waterproofed in tile phase |
Likely hidden costs
Rot behind tub or subfloor after demo · Moving drain/vent stack (wet-wall move) · Lead or asbestos in older homes · Custom glass lead times (2–4 weeks)
Bathroom remodel plan
Budget $18,243 – $22,703 · 3–7 weeks
Pre-sign checklist
- Written scope matches layout and shower type selected
- Permit applicant named on contract
- Three references called (jobs 6–18 months ago)
- COI from agent with you as certificate holder
- Deposit within state cap
- Line-item quote received (not lump sum only)
Questions for contractors
- Who pulls permits and schedules inspections?
- Are fixtures owner-supplied or contractor-supplied with model numbers?
- What is excluded if mold or soft subfloor is found?
- What is the written change-order process?
- What is the payment schedule tied to milestones?
What this assumes
- Illustrative defaults — replace with your actual costs and local rules.
Understanding the result
How to use this
Budget range, trades sequence, duration, hidden costs and contractor questions for a bath remodel.